QUESTION: 1
You are a project manager who uses Project Standard 2013. Your manager wants you to plan an office move. You have a project schedule from a prior office move named “OfficeMove.mpp” and you want to Microsoft 74-343 exam use this project to assist in planning the current office move. In the fewest steps possible, you need to create your new project schedule based on the old project schedule. What should you do?
A. Open the old OfficeMove.mpp file, change the project start date and project title, and clear the baseline. Save the file using the current project name.
B. Open the old OfficeMove.mpp file, click on Save As, save the file using a new file name, clear the baseline, and set all tasks to zero percent complete.
C. Open the old OfficeMove.mpp file, save the file as an .mpt file type, removing the baseline and actual values. Save the .mpt file as an .mpp file type, assigning the current project name.
D. Open the old OfficeMove.mpp file, click on Save As, and save the file using a new file name. Then enter the project name in the Project Summary Task. Set all tasks to zero percent complete.
Answer: C
74-343
QUESTION: 2
You are a project manager for an organization that 74-343 vce uses Project Standard 2013. You add shortcuts on the Quick Access Toolbar to your most frequently used commands.
Your manager is impressed with the ease of use this customization provides and would like other project managers in the group to use it. You need to deploy the customization to these project managers. What should you do?
A. Save a Project File with the customizations to the ribbon in the file. Ask the other project managers to open the file.
B. Email your global.mpt file to each project manager. Ask them to place the template in the %appdata%\Microsoft\MS Project\15 \1033 folder.
C. Click on the Import/Export button to export the customizations to a file. Ask the other project managers to import the file.
D. Use regedit to export the following key: HKLM\Software\Microsoft\Office\15.0\User Settings\ProjectRibbon. Ask the other project managers to import the key.
Answer: C

QUESTION: 3
You are a project manager, and your organization uses Project Standard 2013. You have created a non-working day in a resource’s calendar; however, the HR department notifies you that the resource will work that day after all. You need to reflect this change in the project in the most efficient manner. What should you do?
A. Open the Project calendar and mark the work day as working.
B. Open the resource’s working calendar and edit the Work Week details to set the day as working.
C. Open the resource’s working calendar and delete the exception.
D. Open the resource’s working calendar and mark the day as working.
Answer: C

QUESTION: 4
You are a project manager who uses Project Professional 2013. All resources in your project schedule have availability of 8 hours per day. You notice that several of the resources on the project are over allocated. You decide to level the project to 74-343 pdf help resolve the overallocations for the resources. Team members often do not work at the same time when completing their work on the tasks. You need to resolve the overallocations by using the Resource Leveling function. What should you do?
A. Click the Level only within available slack option.
B. Click Clear Leveling.
C. Click the Leveling can adjust individual assignments on a task option.
D. Click the Level resources with a proposed booking type option.
Answer: C

QUESTION: 5
You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization’s scheduled two-week closure. You need to 74-343 dumps reflect the closure within your schedule. What should you do?
A. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.
B. Open the Project Calendar and modify the default work week by setting the dates as non-working time.
C. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.
D. Open the Project Calendar and enter the planned closure in the Exceptions tab.
Answer: D

Read more: http://www.passitdump.com/74-343.html The Microsoft 74-343 exam practice questions and answers covers all the knowledge points of the real exam. We update our product frequently so our customer can always have the latest version of the brain dumps. We have the most professional expert team to back up our grate quality products. If you still cannot make your decision on purchasing our product, please try our free demo.